Thursday, March 12, 2009

Water Line Replacement Street Closure Schedule

Start Date: Monday, April 6, 2009 End Date: Friday, June 12, 2009


Week #
Date
Street Area
Block #
Closed Intersection(s)

1
April 6 - 10
Aspen St. to Oak St.
300 west
Aspen & Oak St. / Colorado Ave.

2
April 13 - 17
Aspen St. to Oak St.
300 west
Aspen & Oak St. / Colorado Ave.

3
April 20 - 24
Oak St. to Fir St.
200 west
Fir St. / Colorado Ave.

4
April 27 - May 1
Oak St. to Fir St.
200 west
Fir St. / Colorado Ave.

5
May 4 - 8
Fir St. to Pine St.
100 west
Pine St. / Colorado Ave.

6
May 11-15
Fir St. to Pine St.
100 west
Pine St. / Colorado Ave.

7
May 18 - 22
Pine St. to Spruce St.
100 east
Spruce St. / Colorado Ave.

8
May 26 - 29
Pine St. to Spruce St.
100 east
Spruce St. / Colorado Ave.

9
June 1 - 5
Spruce St. to Willow St.
200 east
Willow St. / Colorado Ave.

10
June 8 - 12
Spruce St. to Willow St.
200 east
Willow St. / Colorado Ave.



Where? Colorado Avenue travel way from Aspen St. intersection through Willow St. intersection. Some sidewalks and curb and gutter will be included, as well, when water service lines require replacement. Pedestrian access will be provided to all open businesses.


What can you do to help us work quickly & safely?

Please, respect all street closures when in your car, on a bicycle, or on foot (or on a moped, on a skateboard, etc., etc.). This will help our contractor maintain a safe construction site and work more quickly to stay on schedule or finish early.